Kai Tak Sports Park 85% complete



Linkedin
Twitter

Kai Tak Sports Park Stadium construction update Image: Kai Tak Sports Park

The under-construction Kai Tak Sports Park in Hong Kong has hit a significant milestone with the successful completion of the Main Stadium exterior building façade panels.

The developers said the momentous accomplishment represents a truly world-class architectural feat, which has created an iconic structure that adds to the new skyline of Victoria Harbour at Hong Kong Kowloon East.

Kai Tak Sports Park is a fully integrated sports, leisure and entertainment destination. The 28-hectare Sports Park forms part of the redevelopment on the site of the old Hong Kong International Airport in Kai Tak.

The Sports Park features a 50,000-seat Main Stadium with a retractable roof, an Indoor Sports Centre with the flexibility to host community sports and events of up to 10,000 seats, and a Public Sports Ground with a capacity of 5,000 seats.

These venues will be complemented with extensive public open spaces for events and leisure together with retail and harbour front dining spaces.

Designed with the theme “Pearl of the Orient”, the Main Stadium proudly showcases a meticulously crafted surface formed by about 27,000 aluminium panels as part of the multi-layered façade, each shaped into signature design triangular pieces, adding to its unique visual appeal.

The unique colour of façade design is capable of shifting to different colour hues including mountain blue, metallic purple, metallic silver and other colours depending on the degrees of brightness of natural daylight.

This transformative feature lends a contemporary and cosmopolitan aura to the district. Leveraging pioneering proprietary coating technology, the “pearlescent” coloured panel surfaces have also been endowed with self-cleaning capabilities and long-lasting durability, effectively combating the impact of dust and rainwater on the exterior walls.

This represents an unsurpassed commitment to design excellence, functional superiority and advancements in industry technology, the developers said.

Throughout the course of the design and construction process, the project team actively employed various advanced digital technologies for incorporation into a comprehensive Building Information Model (BIM).

This model served as a robust platform for data analysis and verification, seamlessly integrating all facets of the exterior façades, including the external structure, dimensions of triangular panels, and other related building components, such as glass wall and LED façade lighting, etc.

Through a process of meticulous adjustments and refinements to the actual dimensions and installation positions of the triangular panels, the team successfully reduced the original panel quantity of over 47,000 panels to just 27,000 panels for the 50,000-seat Main Stadium.

Kait Tak Sports Park management added, “This accomplishment serves as a distinctive illustration of our adherence to the 3S concept of Standardization, Simplification, and Single Integrated Element during the planning design and construction process, with a view to enhancing efficiency of work execution, minimizing the need for extensive field works and ensuring effective budget control.

“With these measures, installation of the façade panels for the entire Main Stadium only took just eight months. In anticipation of the substantial completion of nearly 85 percent of the construction works, the Kai Tak Sports Park is now stepping into its final stage of construction.”

Kai Tak Sports Park is poised to become a vibrant and magnetic sports hub in the near future for promoting sports in the community, supporting elite sports and promoting Hong Kong as a centre for major international sports events.

Distinguished by a wide variety of international standard sports facilities and captivating design, the Park will become one of the unparalleled sports infrastructures for hosting China’s highly anticipated 15th National Games in 2025 jointly hosted by Guangdong, Hong Kong, and Macau.

John Sharkey, Project Director of Kai Tak Sports Park said, “The completion of the exterior wall works at Kai Tak Sports Park represents a remarkable milestone, showcasing our project team’s unwavering commitment to excellence and their relentless pursuit of creating a world-class sports and entertainment destination.

“This achievement not only transforms the iconic skyline of Victoria Harbour but also signifies significant progress towards our vision of establishing a premier sports hub. Anticipating the arrival of athletes, sports enthusiasts, and visitors from around the globe, we eagerly look forward to sharing the extraordinary allure of Kai Tak Sports Park.”

As the largest sports infrastructure project in Hong Kong, the major facilities within the precinct are expected to be completed in phases by the end of 2024 for opening in 2025.

Continue to follow Coliseum for latest updates on venues business news. Coliseum is dedicated towards building the best global community of sports and entertainment venue executives and professionals creating better and more profitable venues.

Become a member of the only Global Sports Venue Alliance and connect with stadiums, arenas and experts from around the world. Apply for membership at coliseum-online.com/alliance and make use of the 365Coliseum Business.

Watch 380 member-exclusive videos with valuable tips for your venue



« Previous News:
» Next News:


Advertisement
Advertisement
Advertisement